Construction
Update
 |
| Construction workers prepare to install a window
in the new Joan and Joel Smilow Research Center,
which will be completed by the end of 2005. |
Smilow Research Center
Construction of
the Joan and Joel Smilow Research Center remains on schedule.
The steel superstructure and concrete floors were completed
in January. Exterior brickwork has progressed above the
10th floor and installation of the curtain wall exterior
continues. The building is weathertight from the eighth
floor down, allowing interior work on the lower floors.
Construction will be completed by the end of 2005, and
the structure will be ready for occupancy by early 2006.
Rusk Institute
A renovation was recently completed on the first floor
of the Howard A. Rusk Institute of Rehabilitation Medicine.
Two deluxe private rooms were created, several four-bed
rooms were converted into two-bed rooms, lighting was
enhanced, patient bathrooms in rooms and corridors were
upgraded, and two nurses stations were renovated. |